Lindsey Street – Elm Avenue to Jenkins Avenue

Project Scope of Work:

This project is located along Lindsey Street from Elm Avenue to Jenkins Avenue.  The primary purpose of the project is to reconstruct the existing 3-lane roadway and to provide drainage improvements.  Other improvements include new curb and gutter, a raised center median, improved pedestrian crossings, segments of new ADA sidewalks, traffic signal modifications at Elm Avenue and pedestrian signals at Asp Avenue. 

 

Projected Schedule

  •          Final Plans and Cost Estimates – December 2026

  •          Open Bids – FFY 2028

  •          Begin Construction – FFY 2028

  •          Complete Construction – FFY 2029

 

Project Funding

  • Bond Funds

  • ACOG Funds