Lindsey Street – Elm Avenue to Jenkins Avenue
Project Scope of Work
This project is located along Lindsey Street from Elm Avenue to Jenkins Avenue. The primary purpose of the project is to reconstruct the existing 3-lane roadway and to provide drainage improvements. Other improvements include new curb and gutter, a raised center median, improved pedestrian crossings, segments of new ADA sidewalks, traffic signal modifications at Elm Avenue and pedestrian signals at Asp Avenue.
Projected Schedule
Final Plans and Cost Estimates – December 2026
Open Bids – FFY 2028
Begin Construction – FFY 2028
Complete Construction – FFY 2029
Project Funding
Bond Funds
ACOG Funds